Resources Assigned to a Parent Task

Avatar

Level 3

Hi community,

what is the appropriate filter to use to identify where resources are assigned to a parent task?

 

Thanks 

mesh 

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

I would go with filtering for any task where the number of children is greater than 0.