How can I resolve task dependencies not updating automatically in Adobe Workfront?

Avatar

Level 1

I’m encountering an issue where task dependencies in Adobe Workfront are not updating automatically when changes are made to predecessor or successor tasks. This is causing discrepancies in project timelines and confusion for the team. Has anyone experienced this problem, and if so, how can I fix it to ensure dependencies update correctly?"

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

@AlexRose691 - I would double check that your projects update type is not set to manual.

 

KellieGardner_0-1735586911078.png

 

Project Update Type overview | Adobe Workfront




View solution in original post

3 Replies

Avatar

Correct answer by
Community Advisor

@AlexRose691 - I would double check that your projects update type is not set to manual.

 

KellieGardner_0-1735586911078.png

 

Project Update Type overview | Adobe Workfront




Avatar

Community Advisor

@AlexRose691 - please let me know if that solved your issue or if you need additional help.




Avatar

Community Advisor

 

Hi @AlexRose691,

 

In addition to the Update Type suggestion @KellieGardner mentioned, it might also be good to review this Recalc Timelines primer, and if you are using cross project predecessors, I'd also invite you to learn about some gotchas in this video about our Recalc Helper solution.

 

Regards,

Doug