Hi Community,
I'm curious to know why some predecessors relationships showing green and black? see attached screenshot for detail.
Thanks
Mesh
Solved! Go to Solution.
Views
Replies
Total Likes
Green means the predecessor task is complete and black means the predecessor task is not complete yet.
Example below:
Tasks 3 and 4 are both complete and you can see they are green but the others are not complete yet so they are still black.
Views
Replies
Total Likes
Green means the predecessor task is complete and black means the predecessor task is not complete yet.
Example below:
Tasks 3 and 4 are both complete and you can see they are green but the others are not complete yet so they are still black.
Views
Replies
Total Likes
@KellieGardner perfect! Thank you so much. Very informative.
Views
Replies
Total Likes
Views
Likes
Replies