Predecessor Hack

Avatar

Level 10

Hi folks,

Here's a hack I invented out of necessity to make it a bit easier to edit the (tiny) "pills" on existing predecessors on projects with cross project predecessors, lags, and/or (but especially) tasks with multiple predecessors.

Regards,

Doug

0694X00000FUUQhQAP.png

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

2 Replies

Avatar

Level 3

Hi @Doug Den Hoed‚ , very cool! Is this a text mode hack? And if so, did you share the code somewhere?

Avatar

Level 10

Thanks Cathy,

Nope, it's even easier: simply create two columns in your view that refer to Predecessors, and use the leftmost (editable) to make changes, and the rightmost as a reference. #WhyDidntIThinkOfThisSooner

Regards,

Doug