Help with "Predecessor Complete" = Yes when the predecessor is not complete

Avatar

Level 1

I found that the “Predecessor complete” is showing Yes when a predecessor is not complete, here is an example of that on a project:

Project = https://barclaysus.my.workfront.com/project/67ec012623b06b3f9d1b5d8eb0506c2d/tasks

Here is a screenshot, where I brought in “Predecessor Complete” and “Can Start”

 

Can you please help us understand why Predecessor Complete = Yes when it is not ready to start?

Are we missing something on this one?

 

 

KarrieLo1_0-1746024430791.png

 

Thank you for your help!

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Reply

Avatar

Community Advisor

we don't have a Predecessor Complete field. Is this a custom field on your side, or a calculated column? If so, what does it relate to?