I found that the “Predecessor complete” is showing Yes when a predecessor is not complete, here is an example of that on a project:
Project = https://barclaysus.my.workfront.com/project/67ec012623b06b3f9d1b5d8eb0506c2d/tasks
Here is a screenshot, where I brought in “Predecessor Complete” and “Can Start”
Can you please help us understand why Predecessor Complete = Yes when it is not ready to start?
Are we missing something on this one?

Thank you for your help!