Expand my Community achievements bar.

Interested in getting an Adobe Workfront certification? Don't miss our AMA on June 10th, where our experts will be available to answer any questions you may have about getting certified!
SOLVED

Timeline updates not reflecting with predecessors set

Avatar

Level 1

I have a project set up where each task has a predecessor so that the timeline will auto update when one change is made to a task. We are seeing this break where even though we change the date, the following tasks are not reflecting the change to start date even though the predecessor is set properly. Additionally, when we have multiple tasks with the same predecessor, it will sometimes only change one tasks start date not all of the linked tasks.

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

Hi Bailey - Those are also prescriptive constraint types, sorry I misled you by saying only "must". Here are details on the constraint types to help in the future. Basically, anytime you are hand-picking a start or end date of a task it's overriding the predecessors.

 

https://experienceleague.adobe.com/en/docs/workfront/using/manage-work/tasks/task-constraints/task-c...

 

To keep the default timeline with your predecessors, it's best to use the following constraints.

  • As Soon As Possible
  • As Late As Possible
  • Earliest Available Time
  • Latest Available Time

 




View solution in original post

7 Replies

Avatar

Community Advisor

I would double-check the task constraint type to make sure they aren't set as any kind of "must" type. Workfront essentially ignores any predecessor relationships of the task with those constraint types. 

 




Avatar

Level 1

I switched it to Start no later than and Fixed Dates and it still didn't update to reflect the predecessor timing.

Avatar

Level 4

I believe ASAP is the only constraint that will allow timelines to be auto updated.

Avatar

Level 1

This worked! Thanks!

Avatar

Correct answer by
Community Advisor

Hi Bailey - Those are also prescriptive constraint types, sorry I misled you by saying only "must". Here are details on the constraint types to help in the future. Basically, anytime you are hand-picking a start or end date of a task it's overriding the predecessors.

 

https://experienceleague.adobe.com/en/docs/workfront/using/manage-work/tasks/task-constraints/task-c...

 

To keep the default timeline with your predecessors, it's best to use the following constraints.

  • As Soon As Possible
  • As Late As Possible
  • Earliest Available Time
  • Latest Available Time

 




Avatar

Level 4

@BaileyKi - have you confirmed your project settings > Update Type is set to Automatic and On Change?

Avatar

Level 1

Yes it is set to "Automatic and On Change"