내 커뮤니티 업적 표시줄을 확대합니다.

Don’t miss the Workfront AMA: System Smarts & Strategic Starts! Ask your questions about keeping Workfront running smoothly, planning enhancements, reporting, or adoption, and get practical insights from Adobe experts.
해결됨

Marking work complete with light license

Avatar

Level 1

Is it possible to mark task work complete if you only have Light license level?  Is this only possible if you have a Standard license level even if you have manage or contribute access to a project? 

1 채택된 해결책 개

Avatar

정확한 답변 작성자:
Community Advisor

@BethHolzman you are correct, Light users cannot mark work complete.

Access level documentation includes this note:

"Users with the Light access level:

  • Can be assigned work items but can’t complete them."

Forces users who will be actively working on projects into the Standard License type.  

원본 게시물의 솔루션 보기

1 답변 개

Avatar

정확한 답변 작성자:
Community Advisor

@BethHolzman you are correct, Light users cannot mark work complete.

Access level documentation includes this note:

"Users with the Light access level:

  • Can be assigned work items but can’t complete them."

Forces users who will be actively working on projects into the Standard License type.