Expand my Community achievements bar.

Submissions are now open for the 2026 Adobe Experience Maker Awards.

Mark Solution

This conversation has been locked due to inactivity. Please create a new post.

Kickstart Project Import

Avatar

Level 1
I am trying to import a large number of projects from another system using the kickstart. One issue I am having is I have set the setScheduleMode to Completion Date, but the import continually sets it as Start Date. Is there another setting I am missing in order to get the Completion Date set on my import? Thanks. Dave Pond
4 Replies

Avatar

Level 8
I got this to work for setting the completion date on the project:

Avatar

Level 2

On a kickstart, to set the setScheduleMode to be the Completion Date; the only value in the spreadsheet (under that heading) should be C. Just the letter C by itself.

Avatar

Community Advisor

Hi, I'll d doing a project import from Jira to WF and we use Start Date completion mode - based on this thread, I assume I have S in the column for this? I've never used a kickstart before, any tips on moving projects (with their tasks) from Jira to WF as brand new projects?

If this helped you, please mark correct to help others : )

Avatar

Community Advisor

@Madalyn_Destafney yes, you can find the Schedule Mode values in the API Explorer under Projects

https://developer.adobe.com/workfront/api-explorer/

 

Heather_Kulbacki_0-1675868236091.png