Need help to write a Report to capture duration (planned v actual) from project start to a specific task name that contains "Design Lock".

Avatar

Level 1

Need help to write a Report to capture duration (planned v actual) from project start to a specific task name that contains "Design Lock".

  • The task "design lock" is used in all projects, but it's used in different templates has different predecessors.
  • I assume I would run a Task report, but can't find a way to capture a task name, or part of a name.
  • I need to report on planned vs. actual durations from the start of the project to the design lock task.
  • And then if the project is cancelled prior to Design Lock, I would report the actual days completed instead of returning an error.

I am new to reports so any help is appreciated. 

1 Reply

Avatar

Level 2

@HeatherTe1 

So, there are couple of ways you can find this:
You can run a task report,
 
1) Add filter Task >> Name Contains "Design Lock".
You'll have all the tasks which contains Design Lock
 
2) Now add new column, switch to text mode and calculate the actual & planned difference in days:
 
displayname=Planned Duration (Days)
valueexpression=ROUND(DATEDIFF({plannedCompletionDate},{project}.{plannedStartDate}))
valueformat=HTML
 
another column for actual:
displayname=Actual Duration (Days)
valueexpression=IF(ISBLANK({actualCompletionDate}), ROUND(DATEDIFF($$TODAY,{project}.{actualStartDate}),1), ROUND(DATEDIFF({actualCompletionDate},{project}.{actualStartDate}),1))
valueformat=HTML
 
It will surely deliver you planned duration & actual duration from starting of the project to design lock completion.
 
Another way is:
Add filter of successor / predecessor >> Name contains Design Lock
and apply the same filters as above to get the exact days.
 
Hope this helps! let me know if you have any questions!