Is there anyway to figure out how long a Project has been on hold (or some other status)?

Avatar

Level 3

Is there anyway to figure out how long a Project has been on hold (or some other status)?

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

Here's an example of filters, if you wanted to pull projects on in a certain status, from a certain date, etc. You'd want to specify the journal entry type is 'edit' to capture status changes.

Madalyn_Destafney_0-1683565247155.png

In your report columns, you can pull the date the entry/change was made.

If you find this helpful, please mark correct to help others : )

If this helped you, please mark correct to help others : )

View solution in original post

3 Replies

Avatar

Community Advisor

Hi there! You can use a journal entry report for this, a journal entry report can track changes in field values, statuses, etc. You can filter to only track whatever you need in certain projects if you want, too.

If this helped you, please mark correct to help others : )

Avatar

Correct answer by
Community Advisor

Here's an example of filters, if you wanted to pull projects on in a certain status, from a certain date, etc. You'd want to specify the journal entry type is 'edit' to capture status changes.

Madalyn_Destafney_0-1683565247155.png

In your report columns, you can pull the date the entry/change was made.

If you find this helpful, please mark correct to help others : )