Expand my Community achievements bar.

The next phase for Workfront Community ideas is coming soon. Learn all about it in our blog!

Is there a way to create a report or using the current Resource feature for displaying recourse over-allocation that would give a quick visual for managers who have resource licensing?

Avatar

Level 2

RESOLVE ISSUE: Felt need for better visual over-allocation report for managers

Identify: Currently the built-in Over Allocation report is a list and numbers rather than visual

Manager needs to be able to look at their direct reports workload and quickly determine where pinch points are

Define:

- Work is assigned from multiple departments

- Numbers do not easily give info to make decisions

- current over-allocation report only goes out to 4 quarters

- granularity is hard with numbers as opposed to chart / lines

- turns RED when over-allocated

- Team Schedule gives a Gannt-type view but, it doesn't give hours just schedule

- If we could just have % Allocation by week and by person

- Display direct reports on the y-axis (left column) and days on the x-axis (across the top)

Solve

- investigate reporting possibilities for over-allocation as above to give a quick visual for managers

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

3 Replies

Avatar

Level 10

Hi - you mentioned Team Schedule, but have your managers looked at Workload Balancer? It can only go out 12 weeks, but you can get hours at the project and task view (and you can even color code based on Project status so you can see what is in planning or on hold as well as current if they'd like that info). There is also a "chart view" at the user level if you prefer that to numbers and then when you expand a person, you can see the hours.

0694X00000DVKqtQAH.png

Avatar

Level 2

The Workload Balancer is a great suggestion, however, we have some departments that plan projects up to 3 years in advance and need to know how to allocate resources for that far in the future. This is what I am struggling with on how to report.

Avatar

Level 10

Hi Duane,

I invite you to consider our Resource Contouring solution (see video), which is designed to handle long range detailed planning and includes a number of visualizations that sound similar to what you're looking for.

Regards,

Doug