Hi All,
Question for the group. We use the workload balancer to fine tune when our team is needed week to week. The typical scenario is that we have a task with one or two resources assigned to it, that task has 40 planned hours spanning a duration of lets say 10 days. That is spread evenly by default week by week in the workload balancer.
The PMs then adjust the hours for what will actually be needed , lets say 30 hours in the first week and 10 in the second week. This works well when there is a resource assigned to the task.
It does not seem to work when there is no resource assigned to the task, and it is just a role assigned. Does anyone know if it is possible to adjust the hours week by week without assigning a resource?
The workaround could be that you have to assign a resource, make the changes, and unassign, but that seems like a lot of work.