I have a project with tasks that have the status of New, have a start date in the future, but they have a progress status of At risk. If I change the status to In Progress, the progress status changes to ON Time. I know that the estimate due date is out in July 2026 but I do not know how to change it.
Here is a snippet of the tasks from the project. Any help would be greatly appreciated
Solved! Go to Solution.
Views
Replies
Total Likes
BillPe,
Take a look at this article it will provide better detail on how the task Progress Status works, https://experienceleague.adobe.com/en/docs/workfront/using/manage-work/tasks/task-information/task-p... so you can check against how your project is set up and how your estimated completion date and any task constraints that may be lurking.
Views
Replies
Total Likes
BillPe,
Take a look at this article it will provide better detail on how the task Progress Status works, https://experienceleague.adobe.com/en/docs/workfront/using/manage-work/tasks/task-information/task-p... so you can check against how your project is set up and how your estimated completion date and any task constraints that may be lurking.
Views
Replies
Total Likes
Do you happen to have the projected start dates as well? Adding that in addition to the task constraints might be helpful.
If the task's projected start date is past the planned start date, that could explain why the tasks are showing as at risk.
Views
Replies
Total Likes
Hi BillPe,
The issue in this case is that there are no predecessors set and I guess your scheduling is done with task constraint "as soon as possible". Since there are no predecessors the system says you should have started working on this already and therefore you are late.
As soon as you enter the predecessors this should be fixed for all except the first task.
Additionally you could change either change the task constraint to as late as possible, but keep in mind this has the risk of users not starting early enough as they are not reminded early. That you need to decide based on your user behavior. Or you change the first task to a fixed must start on date.
Hope this helps.