Hi! For my large campaigns that involve multiple projects, I enter a line item for that project and use a link in the predecessor column. That way, all of the details needed for that project are contained in another request. For example if Campaign A included an Email Journey as one of the many tactics, I would have a line item for Email Journey. Then, a project would need to be entered such as Email Journey for Campaign A in order for me to link it. That one would contain all the tasks for the Email Journey. To actually link to another project, you need to start in Campaign A, open the task, such as Email Journey, click More, then, Predecessors, then select Cross-Project Predecessors on the right. Click Add Predecessor, and then type the project name, Email Journey for Campaign A. You will also need to select the task in Email Journey for Campaign A to trigger completion in Campaign A and I usually select, Final Approval or Uploaded to site. Be sure both are in Workfront before linking. Hope that makes sense and it has helped me simplify the many components of a campaign. If you have question, feel free to email me. Angie Angie Kweder ANSYS-Marketing