Expand my Community achievements bar.

Hi all - for any team using the Workfront DAM, have you figured out a way to show all assets uploaded in a week with thumbnails? We would like to send leadership a weekly report with thumbnails or work pushed to the DAM in a certain timeframe. Thank you.

Avatar

Level 5
 
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Reply

Avatar

Level 2

Hi! You can do this with a Document report filtering on Current Version > External Integration Type and then choose Workfront DAM and Current Version > Entry Date to whichever timeframe you want. There is a Large Thumbnail column that if you use text mode and set the width it makes it slightly larger then the Thumbnail column.