Expand my Community achievements bar.

Latest Community Ideas Review is Out: Discover What’s New and What to Expect!

Gantt Chart View - Month names missing

Avatar

Level 2

Good morning all,

Myself and my colleagues have recently noticed that the months are not displaying on the Gantt chart view of any project we work on. As it has affected several of us, i assume this isn't a user error, but potentially a system change that has caused this.

Does anyone know how to display the months again in the Gantt Chart view? Please see attached a screenshot to see the current view (months should be displaying under 'Quarter').

Thanks in advance

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

5 Replies

Avatar

Level 3

@JamesWi7 

 

that's a bug - day names are missing as well. Have you filed a ticket? 

Avatar

Level 3

@JamesWi7 
Adobe seems aware - i see the same issue. 

Thank you for contacting Adobe Workfront support.

Please note there is an ongoing defect for the missing month and day name from the Gantt chart in the task view.

and

 

. This is a known issue that our development team is currently investigating and working to resolve.

 

Avatar

Level 5

@JamesWi7 

@AMBRNA 

 The fix has been pushed out and I was able to validate that the issue is no longer present


I've confirmed that so - yay

Avatar

Level 5

Per Support: 

 

Good morning! My development team has a fix for this issue that is expected to be released with this upcoming patch on Thursday. I will followup with you then to confirm that the issue is resolved.


@JamesWi7  

@AMBRNA