Is it possible to track all planned complation date of a project? And to list all Previous Planned Completion Date.
Any recommendation. Note: We do not have Fusion yet.
Solved! Go to Solution.
Views
Replies
Total Likes
Hi Kundan,
You can track changes to the project planned completion date via update feeds. You can read more on this here.
When you enabled Project>>plannedCompletionDate as a tracked field, any change to this will record a system update in the updates area of the project. You could then report on this using a Journal Entry report which you can read more on here.
Best Regards,
Rich.