For Project - Possible to track All Planned Completion Date which are changed

Avatar

Level 10

Is it possible to track all planned complation date of a project? And to list all Previous Planned Completion Date.

 

Any recommendation. Note: We do not have Fusion yet.

 

 

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

Hi Kundan,

 

You can track changes to the project planned completion date via update feeds. You can read more on this here.

 

When you enabled Project>>plannedCompletionDate as a tracked field, any change to this will record a system update in the updates area of the project. You could then report on this using a Journal Entry report which you can read more on here.

 

Best Regards,

Rich.

 

 

View solution in original post

1 Reply

Avatar

Correct answer by
Community Advisor

Hi Kundan,

 

You can track changes to the project planned completion date via update feeds. You can read more on this here.

 

When you enabled Project>>plannedCompletionDate as a tracked field, any change to this will record a system update in the updates area of the project. You could then report on this using a Journal Entry report which you can read more on here.

 

Best Regards,

Rich.