Error Message When Adjusting Project Start Time

Avatar

Level 2

Hi!

 

When I am converting a request to a project, I wish to also adjust the start time to start at 8:00AM but every time I try to adjust the time it gives me an error that says "Time must be between 12:00 AM and 11:59 PM." - does anyone know how to fix this/know the correct format for the time?

 

Screenshot 2025-02-25 133408.png

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Level 2

Closing out of all open Workfront windows and reopening a new one fixed the error!

View solution in original post

3 Replies

Avatar

Community Advisor

Interesting error, when I tested it I didn't get an error, and if I do something it just states, "Enter a valid time". This one might be something for Workfront support to help with. 




Avatar

Level 2

Appreciate you trying, thank you!

Avatar

Correct answer by
Level 2

Closing out of all open Workfront windows and reopening a new one fixed the error!