Hi Nick, yes, you can. On the Task Report, once you have added the Planned Completion Date column, click on it, and then click on Advanced Options. From there, you will see a Field Format drop-down menu, where you can indicate how you want this date field to show on the report. There are several options, with two of the options containing the day of the week.
Hi Nick, yes, you can. On the Task Report, once you have added the Planned Completion Date column, click on it, and then click on Advanced Options. From there, you will see a Field Format drop-down menu, where you can indicate how you want this date field to show on the report. There are several options, with two of the options containing the day of the week.