Hi WF Community,

Does anyone know if it's possible to display the day of the week that's associated with a task's Planned Completion Date?

Thanks.

Nick

이 주제는 답변이 닫혔습니다.
최고의 답변: TerryHy

Hi Nick, yes, you can. On the Task Report, once you have added the Planned Completion Date column, click on it, and then click on Advanced Options. From there, you will see a Field Format drop-down menu, where you can indicate how you want this date field to show on the report. There are several options, with two of the options containing the day of the week.

2 답변

TerryHy답변
Level 8
June 22, 2020

Hi Nick, yes, you can. On the Task Report, once you have added the Planned Completion Date column, click on it, and then click on Advanced Options. From there, you will see a Field Format drop-down menu, where you can indicate how you want this date field to show on the report. There are several options, with two of the options containing the day of the week.