Expand my Community achievements bar.

SOLVED

Display Day of Week in Task Report

Avatar

Level 10

Hi WF Community,

Does anyone know if it's possible to display the day of the week that's associated with a task's Planned Completion Date?

Thanks.

Nick

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Level 7

Hi Nick, yes, you can. On the Task Report, once you have added the Planned Completion Date column, click on it, and then click on Advanced Options. From there, you will see a Field Format drop-down menu, where you can indicate how you want this date field to show on the report. There are several options, with two of the options containing the day of the week.

View solution in original post

2 Replies

Avatar

Correct answer by
Level 7

Hi Nick, yes, you can. On the Task Report, once you have added the Planned Completion Date column, click on it, and then click on Advanced Options. From there, you will see a Field Format drop-down menu, where you can indicate how you want this date field to show on the report. There are several options, with two of the options containing the day of the week.