Kannan, Once a request is converted to a project, the status of the request is linked to the status of the project. Once the Project status is changed to "Current" the request's status will change to In-Progress...when the project is complete the request will be marked complete. If you want to report on which ones have been converted to a project, I usually filter on "Resolving Project:Name" is not blank on an Issues Report. I also usually create an issue report that has a column showing the name of the Resolving Projects Name and you can pull in data about that project and the issue making it a pretty handy report to track what is happening with the request and the project in one report. I hope this helps! David
DAVID A. TAYLOR Founder & Managing Consultant