A user left our organization and I want to move all of their assigned tasks to a new user who is taking over their position. Is there a way to do this all at once without having to make the switch project by project? The projects they are in have many different names so I can't use the "name contains" feature for bulk assignments from the workload balancer.
Solved! Go to Solution.
Oh, I can do it via Project Status using the workload balancer.
Oh, I can do it via Project Status using the workload balancer.
Yes! Workload balancer is your friend in this situation for any tasks.
In addition, I would check a report for any active projects they own as well as any proofs they own or are an approver on. Unfortunately these two items cannot be revised through the workload balancer.
++ if they were an active requester you can check for any open requests as well!