Can you link cross-project predecessor to dependent task's project ID/name?
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

2 Replies

Avatar

Level 10
In a task report, you can add the following to reference the name of the cross-project predecessor PROJECT. You can adjust it to pull in other project details as well. displayname=Predecessor Project Name listdelimiter= listmethod=nested(predecessors).lists textmode=true type=iterate valueexpression=IF({isCP}="true",{predecessor}.{project}.{name}) valueformat=HTML

Avatar

Level 2