Can't seem to figure out why Erik Wieseman's To Do list doesn't show some past due tasks. Probably a simple fix, but been unable to figure it out. Need to solve why Erik's work list only shows #1 as a past due task and not #2, #3 and #4. Thanks.
Could be a variation of things. I would start by checking on work that should be showing in the home area widget since those don't seem to appear at all.
Are the tasks complete already?
Are the Projects in a status equivalent to in progress/current?