Calculated field to round up daily hours logged on tasks

Avatar

Level 2

We currently run many projects where we invoice to clients via a separate process, outside of Workfront.

All time that is logged against the respective tasks is rounded up to the nearest half-day, to mitigate the various team meetings and impromptu tasks that might occur throughout the day. Is there a way to automate this within Workfront?

 

Essentially, I'd like to be able to see the actual hours for a task, whereby, on each day, time entered for the particular project is rounded up to the nearest half-day (for us, this being 3.75 or 7.5 hours).

 

Is there a way this could work?

 

Thanks,

 

Alex

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

Hi Alex,

 

The only viable way to achieve this would be with Fusion. You would need to develop a scenario that checks the hours logged against a task/project at the end of each day and then rounds them up appropriately. 

 

There isn't an automated way to achieve this using native Workfront functionality.

 

Best Regards,

Rich. 

View solution in original post

1 Reply

Avatar

Correct answer by
Community Advisor

Hi Alex,

 

The only viable way to achieve this would be with Fusion. You would need to develop a scenario that checks the hours logged against a task/project at the end of each day and then rounds them up appropriately. 

 

There isn't an automated way to achieve this using native Workfront functionality.

 

Best Regards,

Rich.