Calculated Expression - Difference Between Planned and Actual Hours (View)

Avatar

Level 8
Does anyone know the expression required to show the difference between the planned and actual hours on a project and on a task as a view? I am trying to add this to a view on the projects global nav tab and on individual projects, but I can't get it to work. The API seems to have a lot of options for hours, so it I'm probably using the wrong fields and / or my text mode is incorrect because the "Hours Difference" column is returning some weird numbers. Any insight is appreciated! Sydney Sydney Peterson Diversified Communications, Inc.
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Reply

Avatar

Level 10
Hi Sydney, We've got a field created which tells us what's the difference between Planned and Actual Hours. Actual Hours - Planned Hours. Shows a positive number for tasks where the hours are more than expected (i.e. overspent) ROUND((Actual Hours -Planned Hours)/60,2) Hope that helps. Dagmara Garwell BAKKAVOR LTD