Hi,
It's not going to be possible to sum the hours of incomplete tasks at the project form level. You could work out the difference between planned and actual hours across the entire project, but this wont exclude completed tasks.
Your best bet here is to create a task report, filtered to incomplete tasks and grouped by project. You could then sum the planned hours, gicing you the sum of the remaining hours to complete.
Best Regards,
Rich.