I'm fairly new to Workfront. I have a complicated project with at least 3 chains of activities that are within days of being on the critical path. They are hard to identify unless I see the critical path change based on a project update. The slack date isn't helping me. I really want to see the number of days of slack. Does anyone have a way to calculate the number of days of total slack for each task? Therese