Our project templates have multiple job roles assigned to one task. Once we are done assigning people to the project we want to bulk remove all unassigned job roles so that it doesn't affect the Workload balancer. Meaning a task has 6 different job roles that COULD be assigned, but we only need one of those 6 folks working on it and we don't want the planned hours to still be dividing the task by 6 people. Is there a way to bulk remove all unassigned roles?
More context:
We have multiple levels of people doing the same type of work but at greatly varying salaries. (designer 1, designer 2, designer 3 etc) so rather than make their profiles have split job roles we want to have the templates be able to have ANY level working on it, but then just throw out whats not being used once the project is set up.