Hi friends!

 

We have a milestone path we've attached to certain projects. I've gotten a request to create a board where the milestones are the columns. I've searched some, I've played some, but I can't seem to figure it out. Is this possible?

トピック

トピックはコミュニティのコンテンツの分類に役立ち、関連コンテンツを発見する可能性を広げます。

1 受け入れられたソリューション

Avatar

正解者
Community Advisor

hi, this isn't possible. If you create "milestone columns," you would have to manually move the tasks into the relevant column. You're better off creating a report and using the milestone view.

 

元の投稿で解決策を見る

2 返信

Avatar

正解者
Community Advisor

hi, this isn't possible. If you create "milestone columns," you would have to manually move the tasks into the relevant column. You're better off creating a report and using the milestone view.

 

Avatar

Community Advisor

Since @skyehansen confirmed that milestones themselves don't work this way, consider that custom fields at the task level can help. Increasingly I'm finding that milestone paths have more limitations than I like (for example, if your projects have an unpredictable number of content reviews, a custom form means you don't have to generate 20 different Review milestones). The form would include a field that has your milestones and you can reuse those field values (unlike milestones, which are unique). From there, you can filter and organize your Board.

Of course, if you're very entrenched in milestone paths already, that would be quite the shift.