Hi All, What does the community believe is an acceptable/best practice for a minimum number of planned hours for any task? It has been suggested to me that when I plan, all the tasks should have a minimum of 7 (1 working day) planned hours, even if I know the task will only take 1 hour or less. The given reason for this minimum is that the assigned task resource has less filling out to do on their time sheet. To my mind this is excessive and will over inflate the cost and duration of the project. My preference and experience is to have 2 hours, with 3.5 hours as a fall back. I look forward to peoples responses. Martyn Rattray Portfolio Planning Lead.