Baseline Start/Finish Dates

Avatar

Level 3
I want to show how much the project has changed since I created my baseline. I'm primarily looking to show the projected start/finish, which reflects current timing, and the baseline start/finish. I can add the projected start and finish dates to my report. Does anyone know how to include the baseline start and finish dates? Therese
2 Replies

Avatar

Level 10
Hi: You're looking for attributes called "Default Baseline Task: Planned Start Date" and "Default Baseline Task: Planned Completion Date". Thanks, Eric

Avatar

Level 3
You can create a Project report and include the Planned State Date & Planned Completion Date from the Default Baseline table Theresa Gibson Reed Technology and Information Services Inc.