Automate marking a project as complete after all tasks are 100% complete

  • December 7, 2022
  • 1 reply
  • 800 views

Hi everyone! I might be missing something completely obvious but can't seem to find the answer in WF set up.

 

Is there a way to automate a project being marked as 'complete' once all tasks in the project are 100% complete? Some projects are being labelled as late because I have to manually mark them as complete as the planner for our team. 

 

Thanks in advance!

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

Community Advisor
December 7, 2022

HI,

 

In the project settings there is a setting called "completion mode". Set this to Automatic, and projects will then automatically change to Complete once all tasks are marked as complete.

 

Best Regards,

Rich. 

Heather_Kulbacki
Community Advisor
Community Advisor
December 8, 2022

Note, all issues and approvals must also be complete in addition to the tasks in order for the project to auto-complete.

 

But also note, I do very occasionally have the random project where all those things are complete and the project doesn't close itself out even though the completion mode is set to automatic - it's rare but I do stumble across them every now and then.