Assignment Type Report Showing Info Twice for task list with same detail

Avatar

Level 10

Hi

Created Assignment Based Report to collect list of task and assignment, either User or Team.

Why showing the list of task two times with the same info?

Looking for your expertise in this regard. Please refer attachment.

Any recommendation.

Mvh

Kundan.

1 Reply

Avatar

Community Advisor

Hi Kundan,

An assignment report shows every assignment as it's own line item within the report. Since you have two assignments on that task (a user and a team), it is showing two objects in your report.

Best Regards,

Rich.