Yes there are actually a couple of ways to do it. You can simply select all the tasks you want to change (select the first one – hold Shift – select the last one), then hit the Edit button, then Assignment, and make your changes. The other way is to open the project - More tab > Staffing > Scheduling > Swap button, then swap out what you want. Vic Alejandro, PMP, CSM | IT | Sr. Technical Project Manager Denver Water | t: (303-628-7262) | c: (303-319-6473) "http://www.denverwater.org/">