Why is the report with the column 'assigned name' only showing 1 assigned name when there is several names assigned to the task?
How do all the names show?
Why would some assigned names be bold?
Screenshot attached
Thanks
Solved! Go to Solution.
Views
Replies
Total Likes
Hi there, are you in a task report? Using 'assigned to' is always tricky because if multiple people are assigned, it'll only show the primary assignee. Use Task > Assignments to pull all people assigned to the task.
Views
Replies
Total Likes
Hi there, are you in a task report? Using 'assigned to' is always tricky because if multiple people are assigned, it'll only show the primary assignee. Use Task > Assignments to pull all people assigned to the task.
Views
Replies
Total Likes
This solved it! Thank you
Views
Replies
Total Likes
Views
Likes
Replies