Any alternatives that enable light users to Edit tasks or mark them complete

Avatar

Level 2

Are there any alternative methods/ways that can be utilized to allow light users to indirectly make changes to tasks or at least mark them complete. Preferably not using Fusion.

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

RowvillBh1,

That access level won't allow contribute at the project level, unfortunately.  What we do when we're working with agency folks is assure our PM is checking in with them, going through tasks, and our PM validates and updates the project plan for their tasks.  It could work the same way for any light user.

View solution in original post

1 Reply

Avatar

Correct answer by
Community Advisor

RowvillBh1,

That access level won't allow contribute at the project level, unfortunately.  What we do when we're working with agency folks is assure our PM is checking in with them, going through tasks, and our PM validates and updates the project plan for their tasks.  It could work the same way for any light user.