Adding Project Name to Baseline Task Report

Avatar

Level 1
Hi. There may be a very simple answer to this (or maybe not!), but I want to group my baseline task report by Project Name. How do you do that?
2 Replies

Avatar

Level 1
Go ahead and try this in the grouping text mode: group.0.displayname=Project Name group.0.linkedname=task group.0.namekey=view.relatedcolumn group.0.querysort=task:project:name group.0.valuefield=task:project:name group.0.valueformat=HTML textmode=true

Avatar

Level 1
Awesome! Thanks, Zachary. It worked.