Show actual hours in the workload balancer

Avatar

Level 3

9/30/20

We love the new edit allocation feature in the Workload balancer. It would be even cooler if actual hours already logged could be shown, or related to adjusting allocations.


For example, if a task has 20 planned hours, and 5 actual hours were logged on the first day of the task, then the allocation for the remaining days should show the remaining planned hours (15) split across the remaining days, and the first day should show 5 actual hours and not be editable.

3 Comments

Avatar

Level 1

7/12/22

This would be great for our team! When using greater than one-day durations instead of "doing the mental math" it would be nice if it could allocate the appropriate amount of time based on the remaining planned hours and planned duration.

Avatar

Level 1

7/12/22

This would be great for our team! When using greater than one-day durations instead of "doing the mental math" it would be nice if it could allocate the appropriate amount of time-based on the remaining planned hours and planned duration.

Avatar

Level 10

11/2/23

Yes please!
We've had a large number of requests for this (see actuals on the WLB)

It would also be great to have the ability to see burn (planned - actual) per resource, over a given time frame either in the WLB or Resource Planner.