Hi
I have a project where the project-level schedule is set to A.
At the user level, the assignee has a schedule set to B.
The project is configured with "Consider user time off in task durations" enabled.
My understanding is that for a task with this setup (one task, one assignee), the task start and end dates would take both schedule A and schedule B into account.
In other words, if schedule A includes US holidays and schedule B includes UK holidays, the task would start on a day that is not a holiday in either country.
However, in my testing this does not seem to be the case.
Am I misunderstanding how this works?
Views
Replies
Total Likes
here’s a quick tutorial on time off:
I think for what you want, you would need to set it up in the Setup area:
Thanks for sharing the documentation! @skyehansen @Madalyn_Destafney
I’ve followed the steps as outlined.
In Workfront Setup, Calculate Resource Availability is set to use the user's schedule.
In this case:
When the project is generated from the template, I would expect the task to account for holidays from both the US and UK schedules, meaning any holidays in either schedule should be skipped when calculating the task’s start or end date. However, this doesn’t seem to be happening.
I’ve been racking my brain trying to figure out what else could be affecting this, so any insights would be really appreciated.
Views
Replies
Total Likes
I’d take a look at this article explaining schedules and their hierarchy - user vs project schedule, users on the same tasks with different schedules, etc.
@ab_cdef Just checking in — were you able to resolve your issue? We’d love to hear how things worked out. If the suggestions above helped, marking a response as correct can guide others with similar questions. And if you found another solution, feel free to share it — your insights could really benefit the community. Thanks again for being part of the conversation!
Views
Replies
Total Likes
Hi - thanks for the follow-up, but no i was still not able to resolve this issue. The latest update still remains: Re: Consider user time off in task durations - how... - Adobe Experience League Community - 762531
Views
Replies
Total Likes
Views
Like
Replies