Hi @JasminJu,
As a workaround, perhaps you could train your users to leave the browser tab that is performing the file upload and start a separate tab in which they could continue their work (in parallel).
Regards,
Doug
Hi @MikeMcGovernC1,
The graphic below illustrates the P1-P4 Response Time, Resolution Time, and % Compliance requirements from an SLA solution I solved using native Workfront (only) several years ago.
Is this along the lines of what you were after?
Regards,
Doug
Hi @rwinslow,
While you're waiting for this idea to be assessed, I invite you to consider our Magic Reports solution which can preserve such Rich Text items (bullets, underlines, italics, etc.) when exported to pdf.
Regards,
Doug
I'll offer both @ab_cdef,
I believe people value the ability to make their own choices.
Defaulting a selection may seem like a time saver, but it interrupts the pattern of thinking and selecting.
Default values cannot be scrutinized for authenticity, which weakens their validity and usefulne...
Hi @LeonhardWi1,
Typing in Hour Allocations on Tasks (aka "Contouring", or sometimes "Shaping") is certainly an option, and compared to the "two tasks, chained" alternative I mentioned:
allows manually entering allocation hours (e.g. daily), giving precision...but requires manually entering al...
Hi @AbiBeggs,
I see you've marked Kellie's Journal Entry approach correct, so am glad you got what you needed, but would add that -- similar to my original Targeted Auditing post you mentioned, I have in the past also create series of calculated parameters that tracked the cumulative amount of t...
Hi @LauraBa13,
What you're describing reminds me of our Budget Vs Actual Quarterly Burn Report solution, which lets you set each Project’s Annual Requested Amount and Quarterly Budgets, then track and monitor actuals to manage the quarterly dollars and % Burn. We have a monthly version that work...
Hi Folks,
Based on this interesting challenge from @MariaCr2, I'm pleased to share the following technique to easily edit a custom data parameter (e.g. a Tactic Delivery Date on a particular Task) and have it "echo" to its peers (e.g. all other Tasks on the same Project), without Fusion, and alw...