Jennifer, Have you looked at the Task Constraint? In order for predecessors to work correctly to change the dates, the best Task Constraint is "As Soon As Possible". If the Task Constraint of a task is Must Start On, Must Finish On, or Fixed Dates, the predecessor will be ignored with respect to cha...