I agree. It seems incorrect to apply the new rates retroactively to all the hours since inception. This way if the rate changes in 5 years from now, all the hours logged by the resource for 5 years will get multiplied by the new rate. This is especially true of actual costs. Actual costs should be f...
Our organization went through a reorg. As a result, six roles are being merged into 1 new role. We want to -
1.. Discontinue the old roles so that they no longer show up on the new resource estimates. They should show up on the existing projects where resource estimates contain these roles. However,...
Hi,
Thank you both for your suggestions. We could not add milestones to those tasks. However, text mode did the trick.
We had to write text mode to iterate through the tasks on the project and check for a specific task name and put its planned completion date.
displayname=Pol Admin Deploy Da...
Hi,
We have a unique report requirement. Each project has 3 deployment tasks - Deployment 1, Deployment 2 and Deployment 3. We need to create a report which will list each project with planned completion dates of each of the three deployment dates as columns -
Project Name Deployment 1 Date ...
Hi,
We have a requirement to display planned and actual hours on various tasks on the project grouped by Job Role. Idea is to show planned and actual hours for each role assigned to tasks on the project. We tried developing this report but the grand totals never match with the planned and actual...
Hi,
Thanks for your response. This is the closest solution. The only minor drawback will be that the approvers wont be able to correct or enter time for their reportees. E.g. when a reportee is on leave, his manager can enter time for him and approve it. Unfoirtunately, we need this ability. Onl...
Hi Doug, Approvers can navigate to Timesheets tab, search for the closed timesheet and then click Reopen button at the bottom (screen shot attached). If they reopen the timesheet, make changes and then approve it, data will be out of sync.