Hi, 

Can someone please help me in letting know if throttle by day is possible in ACS for email delivery.

 

I am looking to set up a message which is going out to 500 audience per day over a period of 5 days.

 

how can I achieve this?

I did check documentation around this but was unable to find any relevant information.

1 Accepted Solution

Avatar

Correct answer by
Level 5

Hi @mmbb110 ,

 

You can use the "computing the sending date" feature.

 

This allows you to send as 1 delivery, but define different send times for different audiences.

 

Some good and easy to follow instructions are here: https://docs.adobe.com/content/help/en/campaign-standard/using/testing-and-sending/scheduling-messag...

 

Thanks

 

David

View solution in original post

7 Replies

Avatar

Level 1

Hi,

 

You can use wait activity (1 day) after the split activity. 

 

Thanks,

Sumit

Avatar

Correct answer by
Level 5

Hi @mmbb110 ,

 

You can use the "computing the sending date" feature.

 

This allows you to send as 1 delivery, but define different send times for different audiences.

 

Some good and easy to follow instructions are here: https://docs.adobe.com/content/help/en/campaign-standard/using/testing-and-sending/scheduling-messag...

 

Thanks

 

David

Avatar

Level 9
Thanks, I will perform some tests and should be good. will let you know if any issues.

Avatar

Level 9
I followed the steps and my first day send was successful, I am just waiting for the remaining audience to deliver for the next run, my deployment is currently showing as sending retry which is fine but my workflow is showing error at the email step "DLV-490002 Cannot start a new analysis of the delivery since current state ('Retry pending') does not allow it."

Avatar

Level 9

@davidh2892249Thanks, it worked.

 

the only thing that I noticed is the workflow status was in error with the email channel I linked in RED, but it did go out the next day to the intended audience.

is this expected?

Capture.JPG

Avatar

Level 9
David, please disregard my previous comment. I got this working fine. Thanks again.

Avatar

Level 5
@mmbb110 glad you got it working. consulting the logs and tasks section in the workflow action bar is always a good place to start if any workflow activity errors/flashes red.