Hi there!
Combined Entry means a couple things happened at the same time. So someone leaving an update/note while changing the status at the same time, for example.
Scope Change refers to only a project or task (pretty sure), like the duration, planned completion or predecessors have changed. Very specific (instead of just status change, for example).
General Edit is the only one I'm not sure about and having a hard time finding documentation. Wondering if it pulls ANY edit, not a specific edit/change type like above.
If you found this helpful, please mark correct to help others : )
If this helped you, please mark correct to help others : )