What task constraint should I use if I want a date to mimic the date of another task? For example - setting up an email deployment date, they want it to go out the same day as the event - one hour. I want the task to lock into the same date as the event. Thank You! Deb
Solved! Go to Solution.
Topics help categorize Community content and increase your ability to discover relevant content.
Views
Replies
Total Likes
we have 8 hour days. So I would personally try <Number>ff-0.1d but that's just me.
Views
Replies
Total Likes
I could be misreading this but it seems like you're asking more about predecessor dependency and lag:
Have you considered looking at maybe <EventDateTasknumber>ff-1h?
Views
Replies
Total Likes
Hello!
YES, agreed! However, Hourly is not an option for lags. So I'm in a bit of a pickle on this particular task. How do I handle an hour lag if I can't indicate with an hour?
Lags can be the following:
Days
Calendar Days
Percent
Day of the Week
Day of the Week (Non-Zero)
This could be as simple for us as Must Finish On in the date of the event and the email date. That's probably the easiest way to do this. But was hoping to do it with predecessors. If it's not possible, it is what it is.
Views
Replies
Total Likes
we have 8 hour days. So I would personally try <Number>ff-0.1d but that's just me.
Views
Replies
Total Likes
LOL. I feel so silly...it's THAT simple. TYVM! This is the correct answer.