What task constraint should I use if I want a date to mimic the date of another task? For example - setting up an email deployment date, they want it to go out the same day as the event - one hour. I want the task to lock into the same date as the event. Thank You! Deb
解決済! 解決策の投稿を見る。
トピックはコミュニティのコンテンツの分類に役立ち、関連コンテンツを発見する可能性を広げます。
表示
返信
いいね!の合計
we have 8 hour days. So I would personally try <Number>ff-0.1d but that's just me.
表示
返信
いいね!の合計
I could be misreading this but it seems like you're asking more about predecessor dependency and lag:
Have you considered looking at maybe <EventDateTasknumber>ff-1h?
表示
返信
いいね!の合計
Hello!
YES, agreed! However, Hourly is not an option for lags. So I'm in a bit of a pickle on this particular task. How do I handle an hour lag if I can't indicate with an hour?
Lags can be the following:
Days
Calendar Days
Percent
Day of the Week
Day of the Week (Non-Zero)
This could be as simple for us as Must Finish On in the date of the event and the email date. That's probably the easiest way to do this. But was hoping to do it with predecessors. If it's not possible, it is what it is.
表示
返信
いいね!の合計
we have 8 hour days. So I would personally try <Number>ff-0.1d but that's just me.
表示
返信
いいね!の合計
LOL. I feel so silly...it's THAT simple. TYVM! This is the correct answer.