Expand my Community achievements bar.

Wondering how Workfront Proof works? Join our AMA on May 8th and ask our Community experts!

Mark Solution

This conversation has been locked due to inactivity. Please create a new post.

weeks as calendar weeks

Avatar

Level 2
is there a simple way to show duration in weeks as calendar weeks? If I put in 26w starting January 1st, I get Sept 20 as a finish date. I was expecting end of June. So obviously a week is calculated based on 7 work days not 5 work days. Other PM programs (like MS Project) show weeks as calendar weeks, which is what I would expect. (Noted that days are defaulted in WF as WORK days (Mon-Fri) which is what I would expect.) Ideas? Michael Crocken, PMP, MS Mech. Engr. Senior Team Leader, Project Management Whole Foods Market Austin, TX
1 Reply

Avatar

Level 10
Hi Michael, I don't believe the Weeks in Durations are 7 work days. A week would be equal to 5 working days (which still equates to a calendar week). It will all depend on how you define and use your Schedules (NOTE: there's a hierarchy on which schedule is used – i.e. global, project, user levels). You can define your Schedule to be a 5 day work week or anywhere from 1-7 days. Regarding your example, I would suspect the reason your date is much further out than you expect is for a different reason. It could be the aforementioned schedule is not a 5 day work week. It could be because the assigned resource has time-off scheduled in WF. There could be other reasons, but those are the items I would check first. Hope that helps.