I have created a Project report that shows a text mode column for the current task on a project; however, that field comes up blank for some projects. What I've realized is that it is blank because its predecessor task still has an approval pending on it, even though the task itself has been marked complete. With an enforced predecessor, it is not deemed "ready to start". (is that correct logic to begin with?)
Is there a way to show on a Project report if a project has a pending task approval? Even better if it could show the task name and the person who needs to approve.
Edited to add that I've scoured the community/One site and other resources already provided to me and I can't seem to figure this one out on my own.
Thank you!